Eadon Consulting, working in conjunction with SCX, a specialist crane supplier, were asked to provide structural and mechanical verification calculations for a crane that will be used for decommissioning at Sellafield.

Key facts

Location


Sellafield, Cumbria

Client


Sellafield Ltd

In Partnership with


SCX

The crane consists of a typical gantry structure, with two long travel units running on it. The first is similar to a conventional gantry crane hoist, although with a number of modifications to make it suitable for a nuclear application. The second unit however is unusual as it contains a telescopic mast unit that can be extended down into a pond area to enable decommissioning work to be carried out. Mounted on the end of the mast is a Brokk hydraulic arm, onto which various tools can be attached.
Eadon Consulting were asked to independently verify the overall structure of the crane as well as the hoisting and mast mechanisms. In order to provide a cost effective solution, a combination of hand calculations and simple beam element models were used as seismic analysis was not required at this stage.

The biggest challenge of the project was dealing with the large number of different load cases that were possible owing to having two crane units that could move independently on a gantry structure, as well as the various fault loads that could occur. A simple method was developed that enabled all of these load cases to be analysed concurrently, cutting down on analysis time whilst ensuring every case was considered.

Related Projects

Dover Berth 7 Walkway

The projects involved the independent checking of an extension to an existing passenger access brow (PAB) in the Port of...

For more information about any of our projects or services or to discuss your requirements, please telephone 0114 399 0400 or contact us.

Share This